Construction Checklist

 

Use the checklist to learn what is required at each phase of your construction project.

​

​Planning Phase:

 

​Contact us in the Planning Phase for all projects where:​

  • the estimated project value is $5,000,000 and over AND final occupancy is other than 100% core educational use, OR

  • the estimated project value is greater than $30 million, OR

  • there will be demolition work over $750,000, blasting over $750,000, caisson work, tunnelling, airport work (includes helipad), marine work, OR

  • the contract you are using is not listed on the Mandatory Contract Language webpage

  • new build more than 6 storeys AND mass timber, CLT (cross-laminated timber), glulam construction, OR

  • new build more than 15 storeys, any type of construction, OR

  • Delay in Start Up coverage is required to finance repayment of money borrowed for the project, OR

  • the LEG 3 “improvement defects exclusion’ is required, OR

  • more than $10 million Wrap Up Liability coverage is required (such as when the project is in a dense urban area), OR

  • more than 36 months required to finish project

 

Before Procurement

(Before seeking bids from interested companies, such as Professional Consultants, Construction Managers, Design-Builders, or General Contractors)

 

Use our Mandatory Contract Language in your solicitation for:

  • Consulting Professional (Design Services) with an Architect or Engineer

  • Construction Services with a Contractor, Design-Builder, or Construction Manager.​​

  • Contact us if your proposed contract is not shown.

 

Before Construction Work Starts

(The construction insurance must be placed before work starts)

​

Projects with an estimated value under $5 million: 

  • Construction insurance should be placed by the Constructor

  • The Construction Services contract should reflect the requirement for the Constructor to place the construction insurance. 

  • Please contact us immediately if the contract requires the Owner to place the coverage. 

​​

Projects with an estimated value greater than $5 million:

​

Important Notes:

  • It can take at least 6 weeks to place construction insurance coverage, however projects that require referral to the insurer can take longer.

  • If the estimated project value is greater than $50 million it can take 4+ months to place coverage.

​

Before Construction Insurance Ends

 

If you need more time to complete the project:

  • Contact us prior to the coverage expiry date.

 

If the project is complete:

  • Please let us know and send us the final project values within 30 days for the premium adjustment calculations.

 

If the building will not be used for the delivery of core educational services:

  • Please let us know.  We may need to discuss Optional Property Program coverage for the completed building. Optional Property Program coverage is not automatic.  There is an application process.

​Mailing Address:
University, College and Institute Protection Program
Risk Management Branch
PO Box 9405 Stn Prov Govt
Victoria BC V8W 9V1

 

EMERGENCY AFTER HOURS CLAIMS REPORTING: (778) 698-8257

​

Email: Protection.Program@bcucipp.org
Phone: 250 356-1794

Fax: 250 356-6222

The Risk Management Branch acknowledges the territories of First Nations around BC and is grateful to carry out our work on these lands. We acknowledge the rights, interests, priorities, and concerns of all Indigenous Peoples - First Nations, Métis, and Inuit - respecting and acknowledging their distinct cultures, histories, rights, laws, and governments.